RASCI for Project Decisions

When Enterprises embark on large projects, they build out a Project Team. This team consists of Stakeholders, Project Manager(s), EA, TA, SA, Implementation resources and Operations. The challenge happens when Project Decisions need to be made - who makes the call ?

Enter the RASCI. It is a matrix of the key roles, and who should be:
  • Responsible
  • Accountable
  • Supportive
  • Consulted
  • Informed
Assuming we use the RASCI members as defined in the PMLC, we would end up with a table like this:


Stakeholders
Project Manager
Business Analyst
Enterprise Architect
Solutions Architect
Technical Architect
CoE
Operations
Budget 
R
A
S
C
I



Timeline
R
A
S
S
S
I


RACI
I
R
I
I
I
I
I

Project Charter
A
R
S
S
C
I
I
I
Project Plan
A
R
S
S
S
S
C
I
Functional Requirements
I
I
R
A
A
A
C
I
Non-Fuctional Requirements
I
I
R
A
A
A
C
I
Conceptual Acrhitecture

I
S
R
A
A
C
I
Logical Architecture


I
S
R
A
C
I
Physical Architecture



I
S
R
A
I
Detailed Build Plans




I
S
R
A
Runbooks & SOP





I
A
R
Now that the "theory" is out of the way, let's take a look at a practical example:

The project is building out network infrastructure to support a new group being added to the Enterprise. So possible questions which might arise are:
  1. A Stakeholder doesn't want to change the Firewall Rules. Who is authoritative ?
    • The Technical Architect "owns" the Physical Architecture, including decisions about their use & configuration
  2. Who should be informed of a change in Project Scope ?
    • Since the Scope is part of the Project Charter, the Project Manager is responsible to inform every role on the RASCI with a corresponding letter in the matrix. So everybody.
  3. What is the role of the BA in the Detailed Build Plans ?
    • None - there is no corresponding letter in the matrix
As you can see, the roles & responsibilities are clearly defined, so that everybody on the project can determine who "owns" the decision. That's not to say that the project Stakeholders won't over-rule some decisions, but in general they don't.

Sunday, September 13, 2015

Pulling It All Together - CLAP + PMLC

In a series of previous posts, we took a look at various frameworks for bringing valuable IT Services to an Enterprise. Starting with the CLAP Framework, we saw took a look at a basic way of starting with Business Activities and building the necessary Conceptual, Logical & Physical Infrastructures to deliver valuable IT Services.

Next, we saw how to use a tool like the ERRC Canvas to achieve the Enterprise Strategy, by mapping the strategy to goals & objectives. The key function of the canvas is to separate the objectives into four areas: Eliminate, Reduce, Raise & Create. 

Once divided, metric for success are applied, and plans can be created. These plans can be prioritized and dependencies mapped. Getting from Business Strategy to IT Execution is no easy feat - so this post describes a method of execution.

Of course, understanding goals as they relate to Strategy is also very important. We took a look at how to create SMART Goals.
Illustration: CLAP and PMLC Together on One Page

We are now in a position to pull all of those concepts into one diagram, shown above. I have attempted to layer the various concepts together, and embellished them with some extra information, such as when a project can expect to need to engage various roles within the RACI.

Finally, we see three vertical lines which describe a form of IT Governance. In a future post, I will describe the make-up of the ARB/TRB and explain the importance of the Architectural Validation Plan.

Friday, September 11, 2015

Project Management Life Cycle

Illustration: Project Management Life Cycle
We all know that IT projects don't just happen. They usually start with an idea that gets socialized internally, until somebody decides it is interesting enough to write a business case, justifying why the idea might be good for the Enterprise. The Project Management Life Cycle (PMLC) walks the reader, from left to right, through all the components of a project. It assumes the project has been instantiated and has executive sponsorship. Other activities prior to the project itself include the Opportunity Assessment, a Cost/Benefit Analysis, and likely ROI and TCO studies.

The PMLC illustration above is designed to show three things at each stage: the roles that contribute to the project, their responsibility and their deliverable. Starting on the left, the Stakeholders typically sit on a Steering committee, and provide budgetary approvals for the project.

The project is run by the Project Manager, who is responsible for budget, timeline & resources. They usually draft the Project Charter, which defines the objectives and scope of the project. They are responsible for reporting back to, and taking direction from the steering committee. It is their responsibility to deliver the project to successful completion.

The Business Analyst does a lot of leg-work, dealing with the stakeholders to understand requirements, both functional and non-functional. They will take raw data they have collected, and produce information which is valuable to the project, and consumable by all members of the project team.

Now that you have a general idea of the flow, you can interpret the rest of the illustration for yourself. Other information that will later become key is called the RACI. It is an artifact that names all of the roles (as seen in the illustration), and determines who is Responsible, who is Accountable, who is Consulted and who is Informed when a project decision has to be made.

This is a general look at how IT projects move through their life cycle. In a future post, I'll overlay the CLAP Framework, to pull together all of the concepts into a single view.


Thursday, June 14, 2012

ITSM - Defining the Service

This is the second part of my series about my client's ITSM project. Previously, we discussed the challenges associated with chasing shiny objects, and believing that the implementation of a product would solve the client's problems. All too often, ITSM projects fail, because the organization fails to differentiate between a Business-Critical Service and an application.

The first step of the project-plan is defining the Service. This means identifying all of the components which participate in the service. By the ITIL definition, a Service is comprised of People, Processes & Technology. Most IT Professionals will look at the Technology components first. Storage, SAN, inter-networking, and server hardware. Later, the applications which make up the Business-Critical application are considered. There can certainly be many applications involved - even indirectly. Consider how important DNS is to most IT applications.

An outstanding deliverable is the information ABOUT the service - it's owner, it's provider, it's consumers and such. These are key to a later Deliverable, when it's time to start identifying the Service Level Objective/Agreement (SLO/SLA). It is important to start defining these early, even if they may change later. Fortunately, a lot of this information is readily available, or can be discovered during the first phase, which is information gathering.

The key difference between an SLO and an SLA is the concept of the contract. An SLO is an objective the Service Provider will TRY to achieve, but there are no penalties for NOT doing so. In the case of an SLA, there are negative consequences for not achieving the agreed-upon objective.

Once all of the components of the Business-Critical Service are identified and catalogued, the next step should involve classifying the types of logging available. Typically, IT Infrastructure folks will monitor the servers and the applications under their care. They will select "best of breed" solutions which can collect LOTS of different metrics. These generally fall into two categories: Alerts and Data-Points.

Alerts are used to let the Operational Teams know if something is going wrong. These will get triggered if a specific server application ends abnormally, or if a threshold (such as CPU Cycles used) is exceeded. These situations can have disastrous effects on the Business-Critical Application, so the Operations Team needs to act swiftly to remediate them.

Data-Points are pieces of information, collected over time. During the collection, there is no requirement for intervention or action on the part of the Operations Staff. This information collects data ove time, allowing for trending analysis. These can be used or exercises such as capacity planning or show back/chargeback models.

Form a purely technology viewpoint, the tools available today can monitor pretty much anything you can imagine. It is tempting for Management and Executive types to suggest that they want to monitor and alert on everything. The more information, the better, right ? Wrong ! Remember that all of the information that is collected needs to be stored somewhere. The more points of monitoring, the larger the data-store, the more information that needs to be correlated. This effectively slows the system down, unnecessarily.

During the interview phase, it is critically important to capture the Stakeholder's objectives. These could be:

  1. I want to shorten the time to resolve trouble tickets
  2. I want to understand how much it costs for a Business Unit to use the Service
  3. I want to increase the visibility of IT Operations to the Business
  4. I want to be able to demonstrate the availability of the Service
Collecting information that doesn't satisfy one or more of these objectives is of little or no value. So in order to keep the data-store manageable, the points of monitoring & alerting should be kept to the confines of these objectives. If the objectives change later, you can always add to the points of monitoring.

 

 

Saturday, June 9, 2012

Chasing Shiny Objects

Shiny Objects

As my ITSM project continues, I am once again forced to have a series of uncomfortable conversations with my client. It seems that a smooth-talking sales rep has convinced an Operational Manager that they can solve all of their "monitoring and alerting" problems by simply ripping out what they currently have, and implementing a shiny new solution !

Shiny Services

Another Operational Manager has been consorting with a local Services Provider, who promises that if my client simply outsources their monitoring & alerting to them, all the problems will go away. For a low monthly fee ! Just sign a PO Mr Customer, and we can get started right away !

What's a Service ?

Now remember that the ITIL definition of a Service indicates that it is comprised as People, Process and Technology. In the first instance above, it appears that Manager believes he can buy a shiny new object, and all of his problems will go away ! That might speak to the Technology, but delivers nothing for the people or processes. In the second instance, the Manager is hoping to be able to outsource to the Services company, thereby dealing with the people aspect. But the Technology, and possibly the Processes are not being addressed. As such, neither solution deals with the underlying desire to take a "service-oriented" view of the IT Operation.

So in order to address this project properly, we will need to address all three facets of a service: Technology, Processes and People. I have re-ordered them because that is the most logical to me. I see the steps as:

  1. Interview the Executive Sponsors to determine what their objectives are. In essence, I like to ask "What business problem are we trying to solve ?"
  2. Interview the Operations Managers to determine what they see as being success criteria for the project.
  3. Interview the Operations Team Leads. They will provide deep knowledge of the environment, the tools, and the current processes.

Technology

These three sets on interviews will provide the information required for the first phase of the project : Information Gathering & Gap Analysis. The Gap Analysis artifact is the first real Deliverable of the project. Once complete the Gap Analysis will help define what Technology is suited for the overall monitoring needs.

Process

I am in the middle of developing a series of Process Diagrams. These are visual representations of the processes that Operations personnel must go through when a specific condition is detected and alerted upon. There are two diagrams per alert - current state, and desired state. Any gaps between the two are highlighted and root-cause analysis is applied. Typically, these types of exercises uncover communications errors, and/or inefficiencies in the processes.

People

Finally, the thorniest part of the project is examining the People on the various Operations teams. This gets sticky, because the objective is to examine whether or not the team members have the correct skills to perform the Future-State processes, with the tools highlighted in the Technology section. It is never intended as a criticism, but many teams feel threatened by this step.

Summary

So as you can see, an ITSM Project is a lot more than a discussion of how to monitor IT Infrastructure. It involves examining the People and Processes as well as the Technologies. Simply buying and implementing a shiny new technology won't adequately satisfy the objectives of delivering Service-oriented IT.

What's Next ?

In a future BLOG, I will examine the second phase of this project, which involves classifying the collected information into alerts and data-sets, with an eye to event correlation & reporting.